from the data above, compute the prime cost.

  • 📑 Past Questions
  • ⌛ Take CBT exam
  • 📟 Referral
  • 🎫 Support
  • 📢 Earnings
Accounts - Principles of Accounts JAMB 2018
  N
Direct material 2,500
Direct labour 5,000
Direct expenses 1,000
Overhead expenses 1,500

use the information contained in the table to anwser the qustion below;

from the data above, compute the prime cost. 

  • N6,500
  • N 8,500 checkmark
  • N6,000
  • N7,500

The correct answer is: B

Explanation

Prime cost is the direct cost of a commodity in terms of the materials and labour involved in its production, excluding fixed costs. from the table above, prime cos is derivrd thus; Prime cost = direct material + direct labour + direct expenses 

2,500+5,000+1,000=8,500