If 200 layers require 25 kg of layer mash per day, calculate the quantity of feed required by 1,000 layers per day.
5kg
40kg
80kg
125kg
The correct answer is: C
Explanation
No official explanation is available for this question at this time. Please check contributions posted by others below. If you can provide an explanation to help other student learn.